Retro — Bahala Subtypes + Rename

~GO chain complete: ~P ~E ~B ~T ~S ~R

Chain Summary

StepCommandResult
Plan~PBahala subtypes plan — 4 changes, mirror structure
Estimate~EBoard 18 — 5 items, 13 pts
Build~BAll 5 items built in one pass
Test~T8/8 checks pass, no fixes needed
Ship~SLive on bahalaka.com via wrangler
Retro~RThis report

Stats

Commits8 (plan edits + estimate + build + test + ship + retro)
Points shipped13
Test/fix loops0 (clean first pass)
Merge conflicts resolved1 (remote had ~i + ~ul while plan was being written)

What Went Well

What Could Be Better

What's Next

Board 18 is done. Boards 5–17 (app buildout, 208 pts) remain ready when Joey wants to start the WASM/SDK work.